“Six Months Left. No CE Mark. Now What?”

“What?! We don’t have time for that?!” Max stared at the timeline. “Is this how it ends?”

They had done the hard part or so they thought. The product worked. Clinicians believed in it. But now they were facing a different kind of challenge: turning that working product into a CE-marked medical device before their runway ran out. And with their next funding round tied to regulatory progress, the risk became existential.

Max had been running VenaSense Medical with a small, young, and enthusiastic team. The idea originated from one of the co-founders, an emergency physician, who had repeatedly faced the same challenge: establishing intravenous (IV) access in critically ill patients. In high-pressure situations, identifying a viable vein is often difficult, leading to multiple failed attempts, delays in treatment, and unnecessary patient discomfort.

(This case is fictional but based on one of our recent clients; details have been changed and any resemblance to actual people or organizations is incidental.)

Early Progress and Early Missteps

It had been a long journey. At first, the team worked on proof-of-concepts part-time, alongside their day jobs. Later, after securing initial funding, the team slowly grew into a mix of experienced engineers and people just starting their careers. None of them, however, had experience building and clearing medical devices.

Initially, they brought in consultants from one of the large MedTech consultancy firms. Max had not been impressed. During the acquisition phase, the senior consultant made a strong impression. But once the real work started, the team was handed off to a junior with limited experience. Progress on the QMS was slow. The team had many questions about what to document and how, but the support remained high-level and superficial. Given the costs, they decided to continue mostly on their own.

      Technical Wins, Regulatory Setbacks

The first clinical tests were positive, and users were enthusiastic. However, technical development moved much slower than expected. In particular, ensuring the hardware could survive repeated sterilization cycles proved far more challenging than anticipated.

Meanwhile, the quality team continued implementing the QMS, and the notified body process moved forward. They successfully passed the Stage I audit—procedures were in place. But during the multi-day Stage II audit, the design verification and validation were not yet complete. The auditors issued a major non-conformity: the company could not demonstrate effective implementation of its processes. They were given six months to close the gap or restart entirely.

They didn’t make it in time.

Disappointed and frustrated, VenaSense formally withdrew their application.

 

A Product That Finally Works—But Time Runs Short

At the same time, real progress was being made. The redesigned product passed re-sterilization testing. An experienced MedTech production partner came on board, capable of manufacturing in an ISO 13485-certified facility.

On paper, the worst seemed behind them.

But when they sat down to plan and budget the remaining work, validation testing, technical documentation, and production transfer, it became clear: they needed more time and budget than the six months of runway they had left.

Investors had drawn a firm line: further funding depended on submitting the technical file for conformity assessment and ideally achieving CE marking within 12 months.

Max was frustrated. They were so close, yet still so far away.

The team remained motivated, but struggled with what was truly required and how to efficiently produce the documentation. When the quality manager left, it became clear they needed additional support. Max remained wary of consultants. This time, he wanted to know exactly who would do the work and needed someone embedded enough to guide engineers in making the right decisions and documenting them properly.

Enter MD Squared

This is where we at MD squared got involved. Given the strict timelines, we started with an in-depth review of the existing documentation, focusing specifically on the intended purpose, clinical data, risk management file, and planned testing.

We identified several key changes:

  • Sharpen the intended purpose Clearly define the product as an adjunct, ensuring existing methods remain available.
  • Clarify the risk profile As an adjunct device, risks associated with failure or unavailability could be classified as minor, better aligning with real clinical use.
  • Align software classification (Class A) The software had been developed as Class A, but prior risk controls implied higher-risk classification. By updating the intended purpose and risk profile, Class A remained justified.
  • Certify the in-house prototype line With proper documentation and calibrated tools, in-house assembly could be certified for initial commercial batches—saving time and enabling later production transfer.
  • Leverage existing clinical data Although early data was not collected under EU MDR Article 62, we proposed combining it with bench and literature data into a compliant clinical evaluation report. Risky, but necessary given the timeline.
  • Submit a single combined technical file Instead of splitting into three submissions, we recommended a single file to reduce overhead, cost, and review complexity.

Within a week, we presented our findings and plan to the VenaSense team.

Our proposed support exceeded their available budget. However, by delaying production transfer costs, we created enough financial space. Confident in our approach, we also tied part of our fees to successful submission.

Over the next five months, we worked closely with the team to build the technical file, including the clinical evaluation. In parallel, we helped identify a notified body that could meet their aggressive timeline.

The notified body was initially skeptical. For example, they resisted scheduling the Stage II audit less than 12 weeks after Stage I, based on past experience. We demonstrated readiness—and secured agreement for a six-week interval.

The Outcome

The technical file was submitted on time. The notified body provided initial feedback within 15 days.

The team addressed the (relatively minor) questions within 30 days. After a final exchange, the review was completed in a single round—closing in 63 days.

Meanwhile:

  • Stage I QMS audit passed with minor observations
  • Stage II audit confirmed the in-house production setup was suitable for initial runs
  • Only minor non-conformities were identified, mainly around underutilized processes like CAPA and complaint handling

With corrective actions accepted, VenaSense received its CE mark.

This was less than nine months after they first reached out to MD squared.

With CE marking secured, the company unlocked additional funding and began delivering its first devices. This is not the end of the journey for Max and the VenaSense team, but it is a critical milestone. Because to thrive, you first have to survive.

Conclusion

For any MedTech company, building a product that works, is safe, and is embraced by clinicians requires dedication, persistence, and a bit of luck. But even when all of that is in place, companies can still fail if they cannot navigate certification. This is where we at MD squared B.V. help. Our multidisciplinary approach, covering regulatory, clinical, technical, and QMS considerations, enables informed choices and pragmatic strategies. We specialize in finding creative, efficient paths to initial regulatory approval.

If you are a MedTech company with a working product but struggling to get it certified, feel free to reach out for an introductory call to explore how we might support you.

Erik 02

Erik van Dijk

Managing Partner

Don’t hesitate to ask us your questions.

Drop an e-mail or contact us via LinkedIn

This website uses cookies to ensure you get the best experience on our website. If you want to get more information about this, please view our privacy policy page.